✈️ Exclusive Benefits for Readers
Verified codes to save on your next trip.
The Beijing terminal – Daxing in China is the world's largest new single terminal airport and its construction investment exceeded 11.000 millions of dollars.

In what is planned and will still be under development, the largest passenger terminal in the world opened its doors in China under the name Beijing International Airport. – Daxíng to serve the capital of the most populous country in the world.
Located at large 58 kilometers south of Beijing, It was born as a project aimed at decongesting the main Chinese airport in Beijing. – Capital, which had its inauguration in 1958 and is currently the second airport with the most passengers in the world more than 101 million annually, behind Atlanta with 104 millions.
The massive structure that began construction on 26 from December to 2014 and that makes it the largest single terminal airport in the world, was inspired by a starfish, which highlights its modern architecture and guarantees efficient and environmentally friendly operations.
With an investment that exceeds 11.000 millions of dollars, Its size is equivalent to almost 100 professional soccer fields and has 700.000 square meters of construction.
This terminal hopes to receive a large part of the growing demand from the Asian country, What is projected for the year? 2025 more of 170 million passengers annually between its main airport and the new terminal.
At the moment there are some airlines that have already started operations at this airport, but above all, An increase in frequencies is expected from the most important airlines that will seek to offer flights to both Daxing and Capital.
It is important to note that the airport has all public transportation services such as high-speed train., metro and high-speed expressways along with local bus and taxi services, which will allow effective access for travelers.
Technical characteristics
- Operation type: civil.
- Location: Stop – beijing.
- Opening: 26 September 2019.
- Elevation: 30 meters.
- landing strips: 4 u 8 headers.
- 01L/19R 3,400 meters of concrete.
- 7L/35R 3,800 meters of concrete.
- 17R/35L 3,800 meters of concrete.
- 11L/29R 3,800 meters of concrete.